Follow a batch from its approved instructions to the records that show what happened. Practise handling a missing entry, deciding when a packaging line is ready and tracing a quality control (QC) result back to its sample.
Study for free without an account. Start with the 4 online lessons, then try the worked exercises, A blank entry in the batch record and A previous batch’s label on the packaging line. Finish with the 3-question quiz and get feedback on each answer. This website does not issue a completion certificate for this self-study course.
This course is from Help Me GxP. Meet its co-creators, Adam Walker and Kyle Winn.
Optional companion video course
Three videos explain GMP, the pharmaceutical quality system and change control.
Watch on YouTube (about 22 minutes of video) (opens in a new tab)
Work through the lessons
Tell an instruction from a record
An approved instruction tells a team what to do. A completed record shows what happened to a particular batch. Look for one example of each in the GMP foundations lesson. What question could a reviewer answer from the record alone?
Trace a problem through the quality system
Imagine the same packing check is missed on two shifts. Use the quality systems lesson to identify who records the issue, who considers its effect on the batch and who follows up the action. Think about what would show that the problem stopped recurring.
Decide what must happen before a change
The team wants to replace a paper checklist with an electronic one. Use the change control lesson to identify what needs assessment before the switch. Consider the approved version, access to records and how operators will learn the revised process.
Trace a quality control result back to its sample
Two batches were tested on the same day. How would a reviewer know which batch a result belongs to? Follow the sample identifier through the approved test method, original observations and recorded result. Check which specification applies. If a result falls outside that specification, explain what evidence the team needs to preserve for the investigation.
A blank entry in the batch record
At handover, a required check has no entry. A colleague remembers doing it and asks you to sign the blank space. What can you establish, what should you record and who decides what happens to the batch?
Compare your answer
The blank field establishes that the expected record is missing. It leaves open whether the check took place. Preserve the original entry space and alert the supervisor or quality team under the site procedure. Record what you know, when you found it and any contemporaneous evidence. An authorised person assesses the impact and decides the batch status. If a late entry is justified, it needs its actual date, author and explanation.
A previous batch’s label on the packaging line
During the final check before packaging starts, you find a loose label from the previous batch beside the label printer. The new batch has not started. A colleague suggests putting the label in the bin and signing the checklist. What would you do first? What would you need to see before packaging could start?
Check your line-clearance decision
Keep the line on hold. Preserve the label and record its batch details, where you found it and when. Tell the line lead and involve Quality Assurance according to the site procedure. The team checks the line and printer for other materials, reconciles labels against the packaging records and investigates whether anything else may be affected. Complete and document line clearance using the approved checklist. Start only when the person authorised under the site procedure confirms the line is clear and records permission to start.
GMP knowledge quiz
Choose one answer to each question to see the reasoning. You can try another answer at any time.
Official guidance
- MHRA guidance on good manufacturing and distribution practice
- European Commission GMP guidance, including Chapter 4 on documentation
- EU GMP Part I, Chapter 5, paragraph 5.50 — packaging line clearance (PDF, page 10)
- European Commission GMP Chapter 6 on quality control (PDF)
For tasks at work, follow your organisation’s approved procedures and role-specific training.